Sl.No |
CLient/Consultant |
Project |
Contractor |
1 |
ARAMCO |
Shayba site empty quarter GOSP
* Retrofit and terminations for automation panels and protection relays related to GOSP -1 Substation.
* testing and commissioning of automation panels related feeder protections.
* Modifications and software upgrading (SEL PROTECTION RELAYS) for the total system of the substation.
|
|
2 |
PGCS |
* All types for electrical testing for 13.8 kv SWGR such as:
• HIPOT FOR THE BUSBAR,
• CB TIMING,
• Primary injection,
• CT and VT TEST RATIO VERIFICATION AND etc……,
• Secondary injection,
• BUSBAR INSULATION TEST,
• CR TEST,
• 13.8KV CABLE TESTING,
• TESTING FOR SCHNIEDER PROTECTION RELAYS,
• Commissioning for the13.8kv SWGR panels.
|
|
3 |
ARAMCO |
Wasit gas program site Khorasanya area
* Retrofit and terminations for automation panels and protection relays related to GOSP -1 Substation.
* testing and commissioning of automation panels related feeder protections.
* Modifications and software upgrading (SEL PROTECTION RELAYS) for the total system of the substation.
|
|
4 |
Saudi Electricity Co. (SEC) |
Supply & installation of Emergency D.G & ATS at SEC operational office - South
* Testing & commissioning of Diesel Generator Set 250 KVA, 400V/230V
* Testing & commissioning of ATS 800A
* Testing of LV cables
|
|
5 |
Riyadh Health Affairs |
Electrical Power supply for Admin Building at New Artaweyah Hospital
* Testing & commissioning transformer 1000 KVA, 13.8/0.4 KV
* Testing & commissioning RMU, 3-WAY, 13.8 KV
* Testing & commissioning MV cables
|
|
6 |
ARAMCO |
AL Othmania site 33 substation retrofitting and new protection panels
* Installation for new protection panels (automation panels).
* Removing the old protection panels.
* Cable pulling and termination for that cables as per the schedule.
* Testing and commissioning for the protection relays (SEL 411L, 451, 487E, 311L, GE L90 as per ARAMCO standard.
* PSA signals from the field and from the protection panels.
* RTU signals from the field up to Al Dhaharan centr ARAMCO
|
|
7 |
ARAMCO |
Dammam port SAIPEM ( MURGAN and ZULUF PLATFORM ) 115kv GIS ( HITACHI) 3 bay, 13.8 kv SWGR WESCOSA 20 panels, 480v SWGR
* Installation supervision of protection panels.
* Preparation, documentation, configuration, processing of setting of the relays installed in the protection panels.
* Pre- commissioning, commissioning and energization on plat form of protection panels as per SA ARAMCO standard.
* On site commissioning support
* Protection panel scheme verification as per Protection panels drawing (alarm/operation/status).
* Testing Numerical relays of Line differential protection, Transformer Differential protection and Bus Bar Differential Protection Relays (SEL-311L,GE L90, SEL451 , SEL487E,SEL587Z and SEL751 ).
* Testing of numerical relays P143 ALASTOM for480v.
* Transformer stability for 115kv/13.8kv TRAFO.
* Bus bar stability for 115kv GIS.
* 115kv LCC function test.
|
|
8 |
ARASCO |
Dammam Port (Arasco Factory )
* Installation and supervision for 13.8kv SWGR.
* All types for electrical testing for 13.8 kv SWGR such as:
• HIPOT FOR THE BUSBAR,
• CB TIMING,
• Primary injection,
• CT and VT TEST RATIO VERIFICATION AND etc……,
• Secondary injection,
• BUSBAR INSULATION TEST,
• CR TEST,
• 13.8KV CABLE TESTING,
• TESTING FOR SCHNIEDER PROTECTION RELAYS,
• Commissioning for the13.8kv SWGR panels.
* Total support up to successful energization of the total system and steady state condition.
|
|
9 |
Al Jubail Royal commission |
Jubail AZMEEL ongoing project :
* All types for electrical testing for 13.8 kv SWGR such as:
• HIPOT FOR THE BUSBAR,
• CB TIMING,
• Primary injection,
• CT and VT TEST RATIO VERIFICATION AND etc……,
• Secondary injection,
• BUSBAR INSULATION TEST,
• CR TEST,
• 13.8KV CABLE TESTING,
• TESTING FOR SCHNIEDER PROTECTION RELAYS,
• Commissioning for the13.8kv SWGR panels.
Total support up to successful energization of the total system and steady state condition.
|
|
10 |
ARAMCO |
* All types for electrical testing for 13.8 kv SWGR such as:
• HIPOT FOR THE BUSBAR,
• CB TIMING,
• Primary injection,
• CT and VT TEST RATIO VERIFICATION AND etc……,
• Secondary injection,
• BUSBAR INSULATION TEST,
• CR TEST,
• 13.8KV CABLE TESTING,
• TESTING FOR SCHNIEDER PROTECTION RELAYS, Commissioning for the13.8kv SWGR panels.
|
PGCS |